|
Contract No. CM 04/2024 – Outlying Islands Sewerage Stage 2 – South
Lantau Sewerage Works – Environmental Team Services (2025 - 2027) |
||
|
Monthly Environmental
Monitoring and Audit Report for: December 2025 Revision
6 |
||
|
|
______________ Ting
Po Chung, Ivan Environmental
Team Leader Report
Date: 15
January 2026 |
|
|
|
|
|
Content:
1.2 Environmental
Monitoring & Audit Programme
1.3 Monthly
Environmental Monitoring & Audit Report
2. Basic project
Information and Environmental Status
2.3 Works
undertaken during the Reporting Month
2.4 Drawing
Showing the Project Area, Environmental Sensitive Receivers and Monitoring
Locations
3.2 Environmental
Mitigation Measures
3.3 Environmental
Monitoring Requirements and Contractual Requirements
3.4 Site
Inspection and Audit Reports
4.3 Monitoring
Date, Time, Frequency and Duration
5.1 Completion of Water Quality Monitoring
6.4 Monitoring Date, Time, Frequency and Duration
8. Complaints,
Notification of Summons and Prosecution
10.3 Ecological Impact Monitoring
10.4 Review of the Reasons for and the Implications
of Non-compliance
10.5 Summary of Action Taken in the Event of and Follow-Up on Non-Compliance
Tables:
Table 2.1: Contact Details of Key Personnel
Table 3.1: Summary of Submission Status under
EP-538/2017
Table 3.3: Summary of Environmental Inspections
Table 4.1: Noise Monitoring Equipment
Table 4.2: Noise Monitoring Station
Table 7.1: Summary of
Quantities of Waste Material
Table 8.1: Cumulative Statistics on Complaints
Table 8.2: Summary of
Complaints
Table 8.3: Cumulative Statistics on Successful
Prosecutions
Table 9.1: Construction
Activities and Recommended Mitigation Measures in Coming Reporting 3 Months
Table 10.1: Summary of Ecological Impact Monitoring
Figures:
Figure 2.1 Master Layout
Plan
Figure 2.2 Contract Layout
Plan
Figure 2.3 Locations of
Noise Monitoring Station
Figure 6.1 Mark up Figure
5.4i extracted from approved EIA Report (AEIAR-210/2017)
Figure 6.2 Location Plan for
Temporary Holding Nursery
Appendices:
Appendix 4.1 Calibration
Certificates for Noise Meter and Acoustic Calibrator
Appendix 4.2 Impact Monitoring
Schedule for Construction Phase Noise Monitoring for the Reporting Month and
Next Month
Appendix 4.3 Noise Monitoring
Results and Graphical Presentations
Appendix 7.1 Monthly Summary Waste Flow Table
Appendix 9.1 3 Months Rolling Programme
This Monthly
Environmental Monitoring and Audit (“EM&A”) Report summarise project
monitoring and auditing data, with full interpretation illustrating the
acceptability or otherwise of any environmental impacts and identification or
assessment of the implementation status of agreed mitigation measures,
including monitoring results and findings of the EM&A Programme, along with
findings recorded during the site Inspections and audits, reports of
Complaints, Notifications of Summons and Successful Prosecutions, and other
necessary observations obtained within this reporting month of December 2025.
In the reporting
month, the principal work activities conducted are as follow:
Excavation, sewer
laying, construction of manhole at Pui O Lo Uk Tsuen, South Lantau Road, Chi Ma
Wan Road;
Trenchless drilling
works (Chi Ma Wan Road);
Excavation and Excavation
and Lateral Support (”ELS”) work at Pui O Sewage
Pumping Station (“POSPS”);
Superstructure Reinforced
Concrete (“RC”) works at San Shek Wan Sewerage Treatment Works (“SSWSTW”);
Waterproofing Work at
SSWSTW;
Excavation and Site
formation at SSWSTW;
Electrical and
Mechanical (“E&M”) Installation at POSPS; and
E&M Installation at SSWSTW
Noise Monitoring
Noise Monitoring has
been conducted at 8 of the designated monitoring locations (N12a, N12b, N13,
N14, N15b, N16a, N16b, and N17) where construction works has been conducted
nearby during the reporting month.
Noise
limit level exceedance of 75 dB(A) was recorded at N12a on 24 December 2025.
Site observation recorded a breaker was operating at a roadside works site on
South Lantau Road was observed during monitoring. Also, local traffic noise,
that comprises of heavy vehicles including trucks and buses, was observed to be
high. As such, the exceedance would be due to combination of construction works
and traffic flow. Hence, it is considered that the exceedance maybe project-related.
Repeat
monitoring was conducted on 30 December 2025 due to no construction works
during the public holidays on 25–26 December. Corrected noise level of 72dB(A)
at N12a was recorded. Site investigation conducted on 30 December 2025 observed
that no beaker was in operation at the work site. Corresponding remedial
actions, including reminding the Contractor to maintain vigilance over
construction noise, and formalizing the mandatory erection of noise barriers
for future concrete breaking activities to prevent the recurrence of similar
incidents, have been implemented. The Investigation report is being prepared
and will be reported in the next reporting month EM&A Report.
Water Quality
Monitoring
Subsequent
to the completion of
marine work on 24 May 2025, water quality monitoring was considered completed
by 30 May 2025. No water quality monitoring is conducted in this reporting
month.
Should marine works
resume, water quality monitoring will be conducted in accordance with the
requirement stipulated in the EM&A Manual accordingly.
Ecological Impact
Monitoring
Transplanting of the
trees of Aquilaris sinensis was
completed on 26 April 2022. Maintenance works for trees in holding nursery have
commenced.
As per latest
version of PTP, 4 tree found (1 no. of Aquilaria
sinensis and 3 nos. of Gmelina chinensis) within the site of SSWSTW
which are considered to be the plant species with
conservative importance for temporarily transplanted to the nursery at Kam Tin
and eventually be transplanted to Pui O Pumping Station.
The weekly site
audit was carried out by ET include checking whether good site practices are
being properly implemented by the Contractor.
The extent of the
work site boundaries was checked by the ET during the weekly site audit.
Complaints,
Notification of Summons and Prosecution
No environmental
complaint was recorded in the reporting month.
No notification of
summons and successful prosecution regarding construction works were recorded
in the reporting month.
Reporting Changes
There are no
reporting changes in the reporting month.
Future Key Issues
The
construction works scheduled to be conducted in the coming 3 reporting months
are listed as follows:
Excavation, sewer
laying, construction of manhole at Pui O Lo Uk Tsuen, South Lantau Road, Chi Ma
Wan Road;
Excavation and site
formation at SSWSTW;
Trenchless drilling
works (Chi Ma Wan Road);
Excavation and ELS
work at POSPS;
Superstructure RC
works at SSWSTW;
Waterproofing Work at
SSWSTW;
Retaining wall
construction at SSWSTW;
Slop Work at along the Slop near SSWSTW;
E&M Installation
at POSPS;
E&M Installation
at SSWSTW;
Architectural
Builders Works and Finishes Work (“ABWF”) at POSPS; and
ABWF at SSWSTW
Key construction
activities for the next three months with the recommended mitigation measures
to be implemented are presented as follows:
|
Key Construction Works |
Recommended Mitigation Measures |
|
Excavation, sewer
laying, construction of manhole at Pui O Lo Uk Tsuen, South Lantau Road, Chi
Ma Wan Road;
Excavation and site
formation at SSWSTW;
Trenchless drilling
works (Chi Ma Wan Road);
Excavation and ELS
work at POSPS;
Superstructure RC
works at SSWSTW;
Waterproofing Work
at SSWSTW;
Retaining wall
construction at SSWSTW;
Slop Work at along the Slop near SSWSTW;
E&M
Installation at POSPS;
E&M
Installation at SSWSTW;
Architectural
Builders Works and Finishes Work (“ABWF”) at POSPS; and
ABWF at SSWSTW |
·
Prevention of site runoff during heavy rainstorms. ·
Implementation of noise pollution control in accordance with
Construction Noise Mitigation Plan; ·
Dust control during dust generating works; ·
Adopt surface drainage and sediment control facilities for sewage
installation in village and public roads; ·
Adopt temporary drainage and sediment control facilities on Site; ·
Vehicle wheel-washing and body washing facilities should be provided
at the site entrance; ·
Regular water spraying on excavation works for dust control; and ·
Proper waste handling, recycling and storage. |
1.1.1
The Environmental Protection Department (“EPD”)
completed the Outlying Islands Sewerage Master Plan (“SMP”) Study in 1994 and
drew up a SMP for Lantau Island and other outlying islands. The proposed
sewerage works of the SMP were divided into 2 stages. The Stage 2 Works of the SMP were
subsequently reviewed by EPD under the Outlying Islands Sewerage Master Plan
Stage 2 Review (SMP Review Study) in 2001.
1.1.2
The proposed sewerage works for South Lantau
were further reviewed in 2008 under the Review of Sewerage Scheme for South
Lantau (Review Study). According to the Review Study, the proposed sewerage
works for South Lantau would serve the unsewered areas of Shui Hau, Tong Fuk,
Cheung Sha, San Shek Wan, Pui O and Ham Tin.
1.1.3
The Outlying Islands Sewerage Stage 2 – South
Lantau Sewerage Works, herein referred to as “the Project”, referred to the
sewerage works for South Lantau that would serve the unsewered areas of Shui
Hau, Tong Fuk, Cheung Sha, San Shek Wan, Pui O and Ham Tin.
1.1.4
The Project mainly comprises of the following
items:
a)
Construction of a secondary sewage treatment
works (“STW”) at San Shek Wan in South Lantau;
b)
Construction of sewage pumping station (“SPS”)
at Pui O, San Shek Wan, Cheung Sha, Cheung Fu Street, Shui Hau and Tong Fuk;
c)
Construction of about 1.4km of twin submarine
outfalls with a diameter of 350mm for the disposal of treated effluent from the
STW at San Shek Wan;
d)
Construction of about 10.1km of gravity sewers
with diameters ranging from 150mm to 375mm along South Lantau Road and Chi Ma
Wan Road and at Pui O; and
e)
Construction of about 3.1km of twin rising mains
with a diameter of 200mm to 250mm along South Lantau Road and Chi Ma Wan Road.
1.2.1
An Environmental Impact Assessment (“EIA”) was
subsequently prepared to review the potential environmental impact that would
be due to the Project during its construction works and operational works. The
EIA Report was submitted and approved on 24 April 2017, and Environmental
Permit (“EP”) No. EP-538/2017 was subsequently granted on 13 July 2017.
1.2.2
Environmental Monitoring & Audit
(“EM&A”) Programme is therefore implemented in accordance with the EM&A
Manual under the EIA Report.
1.2.3
Umwelt Consulting Limited (“UCL”) has been
appointed to work as the Environmental Team (“ET”) under EP No. EP-538/2017 to
implement the Environmental Monitoring and Audit (“EM&A”) programme as
stipulated in the EM&A Manual of the approved EIA Report for the Outlying
Islands Sewerage Stage 2 – South Lantau Sewerage Works (Register No.:
AEIAR-210/2017).
1.3.1
This Monthly EM&A Report summarise project
monitoring and auditing data, with full interpretation illustrating the
acceptability or otherwise of any environmental impacts and identification or
assessment of the implementation status of agreed mitigation measures,
including monitoring results and findings of the EM&A Programme, along with
findings recorded during the site Inspections and audits, reports of
Complaints, Notifications of Summons and Successful Prosecutions, and other
necessary observations obtained within this reporting month of December 2025.
1.3.2
The structure of this Report is detailed as follows:
a)
Section 1
Introduction –
Details the scope and
structure of the report.
b)
Section 2 Basic
project Information and Environmental Status –
Summarizes project organization and key personnel contact,
construction programme and works undertaken for the month. Construction
programme, works undertaken during the month with illustrations, drawing showing
the project area, environmental sensitive receivers and monitoring locations.
c)
Section 3
Implementation Status –
Advice on the
implementation status of
environmental protection and pollution
control/mitigation measures, as recommended in the EIA Report and summarised in the
updated
implementation schedule.
d)
Section 4 Noise
Monitoring –
Summarizes the
monitoring results obtained in the reporting period, including monitoring methodology,
name of laboratory and
equipment used and calibration details, parameters
monitored, monitoring
locations (and depth), monitoring date, frequency, and
duration, for impact noise monitoring.
e)
Section 5 Water
Quality Monitoring –
Summarizes the
monitoring results obtained in the reporting period, including monitoring methodology,
name of laboratory and
equipment used and calibration details, parameters
monitored, monitoring
locations (and depth), monitoring date, frequency, and
duration, for impact water quality monitoring.
f)
Section 6 Ecology –
Summarizes the audit
findings during the reporting month on ecological aspects.
g)
Section 7 Waste
Management –
Summarizes the status
of waste management, including the amount and types of waste generated, and
respective treatment approach.
h) Section 8 Report on Complaints, Notification of Summons and Successful Prosecutions –
Summarizes:
Ø Record
of all complaints received (written or verbal) for each media, including locations and nature of complaints
investigation, liaison and consultation undertaken, actions and follow-up procedures
taken, results and summary;
Ø Record
of notifications of summons and successful prosecutions for breaches of the current environmental
protection/pollution control legislations, including locations and nature of the breaches,
investigation, follow-up actions taken, results and summary;
Ø Review
of the reasons for and the implications of non-compliance, complaints, summons and prosecutions including review of
pollution sources and working procedures; and
Ø Description
of the actions taken in the event of non-compliance and deficiency reporting and any follow-up procedures related
to non-compliance.
i)
Section 9 Future Key
Issues –
An account of the future key issues as reviewed from
the
works programme and work method statements.
j)
Section 10
Conclusion –
Summarises the
findings conclusion drawn from the environmental monitoring and audit programme
in this reporting month.
2.1.1
Drainage Services
Department (“DSD”) is the project proponent and the permit holder of the
Project. For the construction phase of the Project, Contractor(s), ET and
Independent Environmental Checker (“IEC”) are appointed to manage and control
environmental issues. Key personnel and contact particulars are summarized in Table 2.1.
2.1.2
Upon conclusion of
Contract No: SD 15/2022 Outlying Island Sewerage Stage 2 – South Lantau Sewage
Works – Environmental Team Services (2023 – 2024), the subsequent contract,
Contract No. CM 04/2024 Outlying Islands Sewerage Stage 2 – South Lantau
Sewerage Works – Environmental Team Services (2025-2027), has been awarded to
Umwelt Consulting Limited (“UCL”) starting 1 February 2025. As such the environmental
team leader (“ETL”) appointed for the Project has been updated to Mr. Ting Po
Chung, Ivan since 1 February 2025. His contact details has been updated in Table 2.1.
2.1.3
There are no other
reporting changes in the reporting month.
Table 2.1: Contact
Details of Key Personnel
|
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
|
Drainage Services Department |
The Engineer for the Contract |
Engineer |
Mr. KK Chan |
2594 7297 |
3104 6426 |
|
Binnies Hong Kong Limited |
Engineer’s Representative |
Resident Engineer |
Mr. Kevin Chan |
3529 3003 |
- |
|
Kwan Lee – Chun Wo Joint Venture |
Contractor |
Sub Agent |
Mr. Daniel Chu |
6737 6701 |
2744 6937 |
|
Environmental Supervisor |
Ms. Joey Pang |
6978 2876 |
|||
|
Environmental Supervisor |
Mr. Philip Wong |
6908 8920 |
|||
|
SMEC Hong Kong |
IEC |
IEC |
Ms. Kitty Lee |
3995 8140 |
3422 3631 |
|
Umwelt Consulting Limited |
ET |
ET Leader |
Mr. Ivan Ting |
3756 9590 |
3582 3310 |
2.2.1
The proposed sewerage
works will collect the sewage generated from the unsewered areas of Shui Hau,
Tong Fuk, Cheung Sha, San Shek Wan, Pui O and Ham Tin in South Lantau (i.e.
within the Project Catchment Area) and convey it to a proposed sewage treatment
works at San Shek Wan for treatment and disposal into outer bay of Pui O / Chi
Ma Wan via a submarine outfall.
2.2.2
The Project was divided into 3 contracts. The current contract, Contract No.
DC/2020/02 - Construction of San Shek Wan Sewage Treatment Works, Associated
Submarine Outfall and Pui O Sewerage Works (“the Contract”) would have the following implementations. The works site of the Contract
is also given in Figure 2.1.
2.2.3
The major components
of the Contract under Environmental Permit (“EP”) (EP No. EP-538/2017)
comprises:
a) Construction of a secondary sewage treatment works
(“STW”) at San Shek Wan in South Lantau;
b) Construction of a sewage pumping station (“SPS”) at
Pui O, San Shek Wan, Cheung Sha and Cheung Fu Street;
c) Construction of about 1.4km of submarine outfall
with a diameter of 350mm for the disposal of treated effluent from the STW at
San Shek Wan;
d) Construction of about 10.1km of gravity sewers with
diameters ranging from 150mm to 375mm along South Lantau Road and Chi Ma Wan road and at Pui O; and
e) Construction of about 3.1km twin rising mains with
a diameter of 200mm to 250mm along South Lantau Road and Chi Ma Wan Road.
2.3.1
In the reporting month, the principal work
activities conducted are as follow:
a) Excavation, sewer laying, construction of manhole
at Pui O Lo Uk Tsuen, South Lantau Road, Chi Ma Wan Road;
b) Trenchless drilling works (Chi Ma Wan Road);
c) Excavation and ELS work at POSPS;
d) Superstructure RC works at SSWSTW;
e) Waterproofing Work at SSWSTW;
f) Excavation and Site formation at SSWSTW;
g) E&M Installation at POSPS; and
h) E&M Installation at SSWSTW
2.3.2
The locations of the works are shown in Figure
2.2.
2.4.1
Noise monitoring location plans with sensitive
receivers are shown in Figure 2.3 and Figure 2.4 respectively.
3.1.1
Mitigation measures according to the
environmental mitigation implementation schedule in Annex A of EM&A Manual
were generally implemented by the Contractor. Hence, the EM&A programme was
considered effective and shall be maintained.
3.2.1
Environmental mitigation measures mentioned the
EIA Report were weekly reviewed and recorded in Weekly Environmental Site Audit
Checklist. Also, a summary of the current status on
submissions and measures mentioned in the EP No. EP-538/2017 are shown in Table 3.1.
Table 3.1: Summary of Submission Status
under EP-538/2017
|
EP Condition |
Submission and Revision No. |
Date of Latest Submission |
|
2.10 |
Waste Management Plan (Rev. 5) (electronic copy) |
4 April 2022# |
|
2.11 |
Preservation and/or Transplantation Plan for Plant
Species of Conservation Importance (Rev. 23) |
9 September 2022# |
|
2.12 |
Compensatory Woodland Planting Plan (Rev. 23) |
15 May 2023^ |
|
2.13 |
Silt Curtain Deployment Plan (Rev. 11) |
1 June 2022# |
|
2.14 |
Landscape Mitigation Plan |
To be confirmed |
|
2.15 |
Construction Noise Mitigation Plan (Rev. 20) |
4 August 2022# |
Note:
^ Submission
was made to EPD
# Approval
from EPD was received
3.3.1
A summary of the current
status on licences and/or permits on environmental protection pertinent
to the Project is shown in Table 3.2.
Table 3.2: Summary of the Current Status
on Licences and/or Permits on Environmental Protection Pertinent to The Project
|
Permits and/or Licences |
Permit. No. / Account No. |
Issued Date |
Valid Period & Expiry Date |
Status |
|
Notification of Works Under APCO |
466408 |
14 Apr 2021 |
N/A |
Valid |
|
Wastewater Discharge Licence under Water Pollution
Control Ordinance |
SSWSTW: WT00039636-2021 |
30 Dec 2021 |
30 Dec 2021 to |
Valid |
|
POPS: WT00039820-2021 |
31 Dec 2021 |
31 Dec 2021 to |
Valid |
|
|
SSWSTW: Gravity Sewer & Raising Main:
WT00042613-2022 |
09 Jan 2023 |
09 Jan 2023 to |
Valid |
|
|
Billing account under Waste Disposal Ordinance |
Account No.: 7040411 |
05 May 2021 |
N/A |
Valid |
|
Registration as a Chemical Waste Producer |
0000-931-K3428-01 |
13 May 2021 |
N/A |
Valid |
|
Construction Noise Permit under Noise Control
Ordinance for SSWSTW |
GW-RS0836-25 |
13 Aug 2025 |
15 Aug 2025 to 12 Feb 2026 |
Valid |
|
Construction Noise Permit under Noise Control
Ordinance for POSPS |
GW-RS0993-25 |
18 Sep 2025 |
27 Sep 2025 to 26 Mar 2026 |
Valid |
|
Construction Noise Permit under Noise Control
Ordinance for Chi Ma Wan Road |
GW-RS0834-25 |
13 Aug 2025 |
15 Aug 2025 to 12 Feb 2026 |
Valid |
Note: Only valid permits or permits under applications
within the reporting month are included.
3.4.1
Within this reporting month, weekly
environmental site inspections were conducted on 1, 8, 15, 23 and 30 December 2025. IEC attended the SSEMC meeting held on 15 December 2025. The ET and
contractor participated in the holding nursery visit for transplanted trees on 15 December 2025.
3.4.2
No non-compliance was found during the site
inspections while reminders on environmental measures were recommended.
Reminders and/or Observations recorded during site inspections in this
reporting month are listed in Table 3.3.
Table 3.3: Summary of Environmental
Inspections
|
Inspection Date |
Reminder and Recommendations |
Close-out Date / Status |
|
24
November 2025 |
Pui O Sewage Pumping Station Reminder1: The
contractor is reminded to improve site tidiness. San Shek Wan Sewage Treatment Works Reminder1: The
contractor is reminded to provide adequate watering for haul roads. |
Contractor has
rectified the reminders on 1 December 2025 |
|
1
December 2025 |
Pui O Sewage Pumping Station No
Reminder and/or Observation San Shek Wan Sewage Treatment Works No
Reminder and/or Observation |
N/A |
|
8
December 2025 |
Pui O Sewage Pumping Station Reminder
1: The
contractor is reminded to regular water spraying on exposed area. Reminder
2: The
contractor is reminded to properly install the tree tag. San Shek Wan Sewage Treatment Works Reminder
1: The
contractor is reminded to regular water spraying on exposed area. |
Contractor has
rectified the reminders on 15 December 2025 |
|
15
December 2025 |
Pui O Sewage Pumping Station Reminder
1: The
contractor is reminded to avoid blockage of permits and licenses at the
entrance of the site. San Shek Wan Sewage Treatment Works No
Reminder and/or Observation Kam Tin Nursery No
Reminder and/or Observation |
Contractor has
rectified the reminders on 22 December 2025 |
|
23
December 2025 |
Pui O Sewage Pumping Station No
Reminder and/or Observation San Shek Wan Sewage Treatment Works No
Reminder and/or Observation |
N/A |
|
30
December 2025 |
Pui O Sewage Pumping Station No
Reminder and/or Observation San Shek Wan Sewage Treatment Works No
Reminder and/or Observation |
N/A |
Note: The reminders given in the last reporting month
on 24 November 2025 were rectified in the reporting month.
4.1.1
The impact noise monitoring should be carried
out at all the designated monitoring stations when there are project-related
construction activities undertaken within a radius of 300m from the monitoring
stations.
4.1.2
The monitoring station shall normally be at a
point 1m from the exterior of the sensitive receiver’s building façade and be
at a position 1.2m above the ground.
4.1.3
Façade measurements were made at the monitoring
locations. For free-field measurement, a correction factor of +3dB(A) will be
applied.
4.1.4
The battery condition was checked to ensure the
correct functioning of the meter.
4.1.5
Parameters such as frequency weighting, the time
weighting and the measurement time were set as follows:
a)
Frequency weighting: A,
b)
Time weighting: Fast,
c)
Measurement time set: continuous 5 mins
4.1.6
Prior and after to the noise measurement, the
meter was checked using the acoustic calibrator for 94dB (A) at 1000 Hz. If the
difference in the calibration level before and after measurement was more than
±1.0 dB (A), the measurement would be considered invalid and repeat of noise
measurement would be required after recalibration or repair of the equipment.
4.1.7
Noise measurements will be made in accordance
with standard acoustical principles and shall not be made in fog, rain, wind
with a steady speed exceeding 5m/s or wind with gusts exceeding 10m/s. The wind
speed shall be checked with a portable wind speed meter capable of measuring
the wind speed in m/s.
4.1.8
Noise monitoring was performed using sound level
meter at the designated monitoring locations. The sound level meters shall
comply with the International Electrotechnical Commission Publications 651:1979
(Type 1) and 804:1985 (Type 1) specifications. Acoustic calibrator shall be
deployed to check the sound level meters at a known sound pressure level. Brand
and model of the equipment is given in Table 4.1.
Table 4.1: Noise Monitoring Equipment
|
Equipment |
Brand and Model |
Serial Number |
Valid Until |
|
Integrated Sound Level Meter |
Rion - NL-52 |
01198668 |
13 Jan 2026 |
|
Rion
- NL-53 |
452008 |
23
Apr 2026 |
|
|
Acoustic Calibrator |
Rion - NC-75 |
34202223 |
13 Jan 2026 |
4.1.9
The calibration certificates of the noise
monitoring equipment are attached in Appendix 4.1.
4.1.10
The microphone head of the sound level meter was
cleaned with soft cloth at regular intervals.
4.1.11
The sound level meter and calibrator were
calibrated at yearly intervals.
4.1.12
The construction noise level shall be measured
in terms of the A-weighted equivalent continuous sound pressure level (“Leq”). Leq(30min)
should be used as the monitoring parameter. Supplementary information for data
auditing, statistical results such as L10 and L90 shall
also be obtained for reference.
4.1.13
For impact monitoring for construction of
village sewers / rising main, noise monitoring should be undertaken on weekly
basis. 1 set of Leq(30min) noise level as 6 consecutive Leq(5min)
between 07:00-19:00 hours on normal weekdays has been taken.
4.2.1
The noise monitoring stations for the Project
are listed and shown in Table 4.2. Impact noise
monitoring was conducted once per week at the noise monitoring stations with
construction works being conducted nearby. Noise monitoring has been conducted
at 8
noise monitoring stations N12a, N12b, N13, N14, N15b,
N16a, N16b and N17 in the reporting month.
4.2.2
Monitoring station N17 Bui O Public School is an institutional sensitive
receiver. During the reporting month, no examination was conducted, as such the
construction noise criteria is 70dB(A).
Table 4.2: Noise Monitoring Station
|
Monitoring Station ID + |
Monitoring Location |
Measurement Type |
Level (in terms of no. of floor) |
|
N01a |
Shui Hau Village |
Free-Field |
G/F |
|
N01c |
Shui Hau Village |
Free-Field |
G/F |
|
N03a |
Tong Fuk Village |
Free-Field |
G/F |
|
N05a |
Residences at Cheung Fu Street |
Free-Field |
G/F |
|
N07 |
Government Holiday Bungalows |
Free-Field |
G/F |
|
N08 |
Cheung Sha Ha Tsuen |
Free-Field |
G/F |
|
N10 |
Cheung Sha Sheung Tsuen |
Façade |
G/F |
|
N11b |
San Shek Wan – Ming Garden |
Free-Field |
G/F |
|
N12a * |
Lo Uk Tsuen |
Free-Field |
G/F |
|
N12b * |
Lo Uk Tsuen |
Free-Field |
G/F |
|
N13 * |
Pui O San Wai Tsuen |
Free-Field |
G/F |
|
N14 * |
South Lantau Community Centre |
Free-Field |
G/F |
|
N15b * |
Pui O Lo Wai Tsuen |
Façade |
G/F |
|
N16a * |
Residences at Ham Tin |
Façade |
G/F |
|
N16b * |
Residences at Ham Tin |
Free-Field |
G/F |
|
N17 * |
Bui O Public
School |
Façade |
R/F |
NOTE:
+ Fine
adjustment of noise monitoring stations at all locations was proposed as per EP
Condition 3.1.
* Measurement
was conducted at the station in the reporting month.
4.3.1
For daytime construction work on normal
weekdays, monitoring of Leq(30min)
should be carried out at each station at 0700-1900 hours on normal weekdays at
a frequency of once a week. Impact monitoring schedule can be referred to Appendix
4.2.
4.4.1
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring
results and graphical presentation can be referred in Appendix 4.3.
Exceedances Recorded
in the Reporting Month
4.4.2
Noise limit level exceedance of 75 dB(A) was
recorded at N12a on 24 December 2025. Site observation recorded a breaker was
operating at a roadside works site on South Lantau Road was observed during
monitoring. Also, local traffic noise, that comprises of heavy vehicles including
trucks and buses, was observed to be high. As such, the exceedance would be due
to combination of construction works and traffic flow. Hence, it is considered
that the exceedance maybe project-related.
4.4.3
Repeat monitoring was conducted on 30 December
2025 due to no construction works during the public holidays on 25–26 December.
Corrected noise level of 72dB(A) at N12a was recorded. Site investigation conducted on 30 December 2025
observed that no beaker was in operation at the work site. Corresponding
remedial actions, including reminding the Contractor to maintain vigilance over
construction noise, and formalizing the mandatory erection of noise barriers
for future concrete breaking activities to prevent the recurrence of similar
incidents, have been implemented. The Investigation report is being prepared
and will be reported in the next reporting month EM&A Report.
5.1.1
Subsequent to the completion of marine
work on 24 May 2025, water quality monitoring was considered completed by 30 May
2025. No water quality monitoring is conducted in this reporting month.
5.1.2
Should marine works
resume,
water quality monitoring will be
conducted in accordance with the requirement stipulated in the EM&A Manual
accordingly.
6.1.1
The weekly site audit
to be carried out by the ET should include checking whether good site practices
are being properly implemented by the Contractor
6.1.2
Impact monitoring of
the transplanted Aquilaris sinensis at
holding nursery and 1 retain tree of Aquilaris sinensis
in SSWSTW Project Site, establishment and after-establishment caring measures
of the compensatory mixed woodland to ensure the affected tree would not be
affected by any unacceptable construction works. The trees would be treated
with establishment works immediately after transplanting.
6.1.3
Site inspection at
the nursery was conducted on 15 December 2025. No reminder was recorded.
6.2.1
The extent of the
work site boundaries should be checked by the ET during the weekly site audit.
Any disturbance by the Contractor outside the works area especially any damage
to the vegetation and surrounding habitats outside the Project area shall be reported
to ER and IEC.
6.2.2
To identify any
unacceptable construction works for the trees of Aquilaris
sinensis during transplanting, establishment and after-establishment caring
measures of the compensatory mixed woodland.
6.3.1
As per latest version
of PTP, 4 trees found (1 no. of Aquilaria sinensis and 3 nos. of Gmelina
chinensis) within the site of SSWSTW (Figure 6.1) which are
considered to be the plant species with conservative importance for
temporarily transplanted to the nursery (Figure 6.2) at Kam Tin and eventually
be transplanted to Pui O Pumping Station.
6.4.1
The recommended good
site practices to be audited once every week as part of the site audit
programme. The weekly site audit to be carried out by the ET includes checking
whether good site practices are being properly implemented by the Contractor.
Results are recorded in Weekly Environmental Site Audit Checklist.
6.4.2
Monitoring programme
for post-transplantation was conducted on 15 December 2025 once per month.
6.5.1
The weekly site audit was carried out by ET
include checking whether good site practices are being properly implemented by
the Contractor.
6.5.2
The extent of the work site boundaries was
checked by the ET during the weekly site audit.
6.5.3
Results and findings of site audit in this
reporting month are listed in Table 3.3.
7.1.1
The quantities of
waste for disposal in the Reporting Period are summarized in Table 7.1. The Monthly Summary Waste Flow Table is shown in Appendix 7.1.
Table 7.1: Summary of
Quantities of Waste Material
|
Waste Type |
Quantity this month |
Quantity (the end of last month) |
Cumulative Quantity-to-Date |
|
Hard Rock and Large Broken Concrete (Inert), in
‘000m3 |
0 |
0 |
0 |
|
Reused in this Contract (Inert), in ‘000m3 |
0 |
0 |
0 |
|
Reused in other Projects (Inert), in ‘000m3 |
0 |
0 |
0 |
|
Disposal as Public Fill (Inert), in ‘000m3 |
0.14 |
0.06 |
30.82789 |
|
Metals, in ‘000kg |
10.5817 |
0.0037 |
124.5716 |
|
Paper / Cardboard Packing, in ‘000kg |
0.0365 |
0.0530 |
1.45978 |
|
Plastics, in ‘000kg |
0.0019 |
0.0051 |
0.11916 |
|
Chemical Wastes, in ‘000kg |
0 |
0 |
0 |
|
General Refuses, in ‘000kg |
84.88 |
70.95 |
1239.66 |
|
Marine Sediment (Type 1 – Open Sea Disposal), m3 |
0 |
0 |
1360.2 |
8.1.1
No environmental complaint was recorded in the
reporting month.
8.1.2
No notification of summons and successful
prosecution regarding construction works were recorded in the reporting month.
8.1.3
Cumulative statistic on complaints, summary of
complaints and successful prosecutions are summarized in Table 8.1, Table 8.2 and Table 8.3 respectively.
Table 8.1: Cumulative Statistics on
Complaints
|
Reporting Period |
No. of Complaints |
|
Project commencement to
the end of last reporting month |
4 |
|
This Reporting Month (December
2025) |
0 |
|
Total: |
4 |
Table 8.2: Summary of
Complaints
|
Date of Notification
from EPD |
Date of Complaint |
Description of Complaint |
Validity of Complaint |
Close-Out Date / Status |
|
26 May 2022 |
22 May 2022 |
A complaint is regarding
to noise nuisance from marine site of San Shek Wan, Lantau Island. |
Based on the
investigation, the works activities of marine works did not result in any
noise nuisance to Noise Sensitive Receivers (NSRs), noise nuisance from the
Project is unlikely to be valid. |
The interim report was
submitted to EPD in June 2022. EPD replied no further comments on the final
investigation report on 13 July 2022. |
|
23 Dec 2022 |
21 Dec 2022 |
A complaint is regarding
to the water quality for Pui O Beach, Lantau Island. |
Based on the
investigation, the works activities at POPS did not result in any water
quality impacts to the Pui O Beach. |
The interim report was
submitted to EPD on 4 Jan 2023. |
|
16 Aug 2024 |
15 Aug 2024 |
A complaint is regarding
to the damaged silt curtain and potential water quality impact. |
Based on the
investigation, no marine works since Dec 2023 till present, the land based works activities at POPS did not result in any
water quality impacts to the Pui O Wan |
The interim report was
submitted to EPD on 31 Aug 2024. |
|
16 Sep 2025 |
16 Sep 2025 |
A complaint is regarding
to oil sheen observed at Pui O Wetland, Lantau Island. |
Based on the
investigation, no evidence of oil leakage within our project site, it is
considered that the oil pollution would not due to
our site operation. As such the case is considered closed. |
The Final Investigation
Report was submitted to EPD by 17 Oct 2025. |
Table 8.3: Cumulative Statistics on
Successful Prosecutions
|
Environmental Parameters |
Cumulative No. Brought
Forward |
No. of Successful
Prosecutions this month (Offence Date) |
Cumulative No.
Project-to-Date |
|
Air |
- |
0 |
0 |
|
Noise |
- |
0 |
0 |
|
Water |
- |
0 |
0 |
|
Waste |
- |
0 |
0 |
|
Other |
- |
0 |
0 |
|
Total |
- |
0 |
0 |
9.1.1
In coming reporting
3 months, the scheduled construction activities are listed as follows:
Ø Excavation, sewer laying, construction of manhole at Pui O Lo Uk Tsuen,
South Lantau Road, Chi Ma Wan Road
Ø Excavation and site formation at SSWSTW
Ø Trenchless drilling works (Chi Ma Wan Road)
Ø Excavation and ELS work at POSPS
Ø Superstructure RC works at SSWSTW
Ø Waterproofing Work at SSWSTW
Ø Retaining wall construction at SSWSTW
Ø Slope Work at along the Slope near SSWSTW
Ø E&M Installation at POSPS
Ø E&M Installation at SSWSTW
Ø ABWF work at POSPS
Ø ABWF work at SSWSTW
9.1.2
The scheduled
construction activities and the recommended mitigation measures for the coming
3 months are listed in Table 9.1. The major construction activities for the next 3 months are summarized
in 3 Months Rolling Programme – February 2026 to April 2026 in Appendix 9.1
Table 9.1: Construction
Activities and Recommended Mitigation Measures in Coming Reporting 3 Months
|
Key Construction Works |
Recommended Mitigation Measures |
|
·
Excavation, sewer laying, construction of manhole
at Pui O Lo Uk Tsuen, South Lantau Road, Chi Ma Wan Road ·
Excavation and site formation at SSWSTW ·
Trenchless drilling works (Chi Ma Wan Road) ·
Excavation and ELS work at POSPS ·
Superstructure RC works at SSWSTW ·
Waterproofing Work at SSWSTW ·
Retaining wall construction at SSWSTW ·
Slope Work at along the
Slope near SSWSTW ·
E&M Installation at POSPS ·
E&M Installation at SSWSTW ·
ABWF work at POSPS ·
ABWF work at SSWSTW |
·
Prevention of site runoff during heavy rainstorms. ·
Implementation of noise pollution control in accordance with
Construction Noise Mitigation Plan; ·
Dust control during dust generating works; ·
Adopt surface drainage and sediment control facilities for sewage
installation in village and public roads; ·
Adopt temporary drainage and sediment control facilities on Site; ·
Vehicle wheel-washing and body washing facilities should be provided
at the site entrance; ·
Regular water spraying on excavation works for dust control; and ·
Proper waste handling, recycling and storage. |
10.1.1 Noise Monitoring has been conducted at 8 of the
designated monitoring locations where construction works has been conducted
nearby during the reporting month.
10.1.2
Noise limit level exceedance of 75 dB(A) was
recorded at N12a on 24 December 2025. Site observation recorded a breaker was
operating at a roadside works site on South Lantau Road was observed during
monitoring. Also, local traffic noise, that comprises of heavy vehicles including
trucks and buses, was observed to be high. As such, the exceedance would be due
to combination of construction works and traffic flow. Hence, it is considered
that the exceedance maybe project-related.
10.1.3
Repeat monitoring was conducted on 30 December
2025 due to no construction works during the public holidays on 25–26 December.
Corrected noise level of 72dB(A) at N12a was recorded. Site investigation conducted
on 30 December 2025 observed that no beaker was in operation at the work site.
Corresponding remedial actions, including reminding the Contractor to maintain
vigilance over construction noise, and formalizing the mandatory erection of
noise barriers for future concrete breaking activities to prevent the
recurrence of similar incidents, have been implemented. The Investigation
report is being prepared and will be reported in the next reporting month
EM&A Report.
10.2.1 Subsequent to the completion of marine work on 24 May 2025, water quality monitoring was considered completed by 30 May
2025. No water quality monitoring is conducted in this reporting month.
10.3.1 Transplanting of the trees of Aquilaris
sinensis was completed on 26 April 2022. Maintenance works for trees in
holding nursery have commenced.
10.3.2 As per latest version of PTP, 4 trees found (1 no.
of Aquilaria sinensis and 3 nos. of Gmelina chinensis) within the
site of SSWSTW which are considered to be the plant
species with conservative importance for temporarily transplanted to the
nursery at Kam Tin and eventually be transplanted to Pui O Pumping Station.
10.3.3 The weekly site audit was carried out by ET include
checking whether good site practices are being properly implemented by the
Contractor.
10.3.4 The extent of the work site boundaries was checked
by the ET during the weekly site audit.
10.3.5 Within this reporting period, holding nursery visit
for transplanted trees on 15
December 2025.
10.3.6 No non-compliance was found during the site
inspection while reminders on environmental measures were recommended. Results
and findings of these inspections in this reporting period are listed below in Table 10.1
Table 10.1: Summary of
Ecological Impact Monitoring
|
Inspection Date |
Reminder and Recommendations |
Close-out Date / Status |
|
15 December 2025 |
Nil |
-- |
10.4.1 The detail of the reasons for and the
implications of exceedance has been discussed in Section 10.1.2.
10.5.1
The detail of action taken in the event of and
follow- up on exceedance has been discussed in Section 10.1.3.
10.5.2
The performance of
the environmental management system of the reporting period was generally
satisfied. Mitigation measures according to the environmental mitigation
implementation schedule and the EIA were generally implemented by the
Contractor. Hence, the EM&A programme was considered effective and shall be
maintained.
10.6.1 No complaints were recorded in the reporting month.
10.6.2
No notification of summons and successful
prosecution regarding construction works were recorded in the reporting month.